We have exciting garage news that I bet you would never guess from the title! Ha. But yes – the slab was poured this week!

We couldn’t easily do much more work before the slab was poured, because we’d prefer that firm surface to put our ladders on, rather than on the soft soil or on boards between radiant heating. It was super annoying to move the boards and ladders around to avoid damaging the radiant heating tubes. S-U-P-E-R.

As fun as this is to set up…

So we did minimal work last weekend. On Sunday, Jen and Troy helped us firm up the framing by installing the rest of the top plates. We also put insulation in under the two door openings.


On Tuesday, Steven and I confirmed everything was secured and aligned for the slab pour. We taped down all of the loose insulation we installed Sunday and the week before. We checked that all the radiant heating tubes were secured, aligned, and the correct distance from one another. We thought it was ready to go!

On Wednesday our contractor arrived to pour the slab. To ensure that the top of the slab is at the correct height (sloping slighting from back to front), they pounded in rebar in an 8′ grid and used the tops of each rebar as a reference height (if you squint you can see them poking up in the photo below).

Then they got started! They quickly figured out that we did not have enough zip ties on our radiant heating tubes (we put them 3′-0″ on center) and the tubes were moving up with the concrete! Steven rushed around adding extra zip ties to keep the tubes down. The tape we used for the loose insulation held it in place, phew.


I wish I would have been working from home to watch them pour. I’m glad Steven was there. He had to be there to make sure the radiant heating tubes weren’t moving, and that the pressure in the system was staying steady (indicating that the tubes had not been punctured).


This is what 5″ of concrete looks like

Steven said they started just before 10:00 am and finished pouring at noon. The steps were as follows:

  • Pour an 8′ section
  • Screed (new word for you!) that section with a 2×4, and use rakes to move the concrete around as needed to make it level
  • Find the reference rebars and pound them down
  • Used a bull float to level the ridges and voids left from screeding, and make it all nice and smooth / use hand floats around the edges of the concrete for the same effect in that location
  • Repeat!

Then they took a pizza break!

After the break, the concrete was cured enough to walk on in the back of the garage where they started. Steven said it was odd to see them leaving footprints on it, but the reason they were walking on it was to use a power trowel to smooth out the top even more. And it did!


You can see the power trowel here

On Thursday they cut control joints in to the slab. Due to shrinkage (hee hee), cracking occurs naturally during the curing process, and the control joints guide where the cracking will occur – hopefully along that joint. The cuts are 3/4″ deep, and Steven checked the pressure on the radiant heating system before and after to make sure no tubes had gotten too close to the surface and been cut by accident. Thankfully, they weren’t! If they had been, we would have been SOL and not able to use that part of the radiant heating… because it’s buried and concrete and there’s nothing we could have done about it at that point.

We know concrete takes time to cure, and we were hoping we could get ladders on it on Friday, but they said to wait until Saturday afternoon. Apparently it gets 95 or 98% of its strength in the first three days, then takes 30 days to fully cure. So when we get ladders up on it, we’ll still put boards underneath, so it doesn’t imprint the concrete. Steven said there is plenty for us to do on Friday without ladders on it just yet.

Previous post: Garage Project: Radiant Heating and Beginning to Frame